Day 38: Wednesday - squeak found and fixed, flooring finished

Chris lifts one of the flooring panels and cuts a trapdoor in it, which allows him to locate the cause of the squeak (folded hanging strap supporting a plumbing pipe) and fix.

He then adds noggins in the wall in the right spots to support the towel rail.

 

Now that the floor is complete it's starting to look like a room, not just a hole in the ground or a derelict building.



Tomorrow, the plasterer comes. Today Chris takes more of the old plaster off the wall as he decides it is not in a good enough state to leave. Once the walls are replastered and the ceiling is skinned, it will really start to look like a room again.